New Senior Building Update - End of February

The past month has seen works progressing towards completion. Staff were given a walk through on Tuesday 25 February with much excitement. Thanks to Greg (Site Manager) for his guided tour. Progress on site includes:

  • External cladding completed
  • Installation of doors and windows completed
  • Wall lining to ground floor & first floor completed
  • Steel walkway structures finalized and roof sheeting installed
  • Ground floor & first floor ceilings completed
  • Installation of joinery & SS benches completed
  • Internal painting completed
  • Scaffolding dismantled
  • Floorcoverings completed
  • Acoustic panels in undercroft installed
  • Services fit off
  • Lock up stage


Check these photos of progress!