Progress on site includes:

  • ·Blockwork to first floor installed and corefilled
  • ·Concrete columns to first floor poured
  • ·Structural steel to first floor commenced
  • ·Walkway bridge to first floor verandah installed
  • ·Landscaping to car park completed and lights connected
  • ·Ground floor wall framing commenced
  • ·Roof trusses install underway
  • ·Stairs to both eastern and western ends of building poured