Latest Senior Building Update
Nov 6th 2019
November update
The past month has seen significant works carried out.
Progress on site includes:
- ·Ground floor columns poured
- Scaffolding erected
- Waterproofing to retaining walls installed
- Ground floor retaining walls backfilled
- Formwork to first floor slab installed
- Reinforcement and post tension cabling to first floor slab completed
- First floor slab poured
- Block work and core filling progressing
- Bitumen to car park installed along with line marking, wheel stops, bollards and lights installed