Latest Senior Building Update

November update

The past month has seen significant works carried out.

Progress on site includes:

  • ·Ground floor columns poured
  • Scaffolding erected
  • Waterproofing to retaining walls installed
  • Ground floor retaining walls backfilled
  • Formwork to first floor slab installed
  • Reinforcement and post tension cabling to first floor slab completed
  • First floor slab poured
  • Block work and core filling progressing
  • Bitumen to car park installed along with line marking, wheel stops, bollards and lights installed

Check out these photos: